MS14: Soft Landscaping – 23 Minilya Project
Milestone 14: Soft Landscaping ๐ Status: In Progress. ๐ Authority: City of Stirling (City of Stirling – Welcome to the […]
Milestone 14: Soft Landscaping ๐ Status: In Progress. ๐ Authority: City of Stirling (City of Stirling – Welcome to the […]
Milestone 13: Hardscaping ๐ Status: In Progress. ๐ Authority: City of Stirling (City of Stirling – Welcome to the City
Milestone 12: Ground Floor Fit-out ๐ Status: In Progress. ๐ Authority: City of Stirling (City of Stirling – Welcome to
Milestone 10: First Floor Fit-out ๐ Status: In Progress. ๐ Authority: City of Stirling (City of Stirling – Welcome to
Milestone 11: Ground Floor Lockup ๐ Status: Completed. ๐ Authority: City of Stirling (City of Stirling – Welcome to the
Milestone 9: First Floor Lockup ๐ Status: Completed. ๐ Authority: City of Stirling (City of Stirling – Welcome to the
Milestone 8: Roof Structure ๐ Status: Completed. Completion Date: 12 November 2025 ๐ Authority: City of Stirling (City of Stirling
Milestone 7: First Floor Brickwork ๐ Status: Completed on 26 September, after bricklaying delays due to the heavy winter rains.
Milestone 6: Suspended Slab Poured ๐ Completed: 20 June 2025 ๐ Authority: City of Stirling (City of Stirling – Welcome
Milestone 5: Ground Floor Brickwork Completed ๐ Date Completed: 11 April 2025 ๐ Authority: City of Stirling (City of Stirling