Milestone 9: First Floor Lockup đź“… Status: Work in Progress. Target Date: 19 December 2025 🏛 Authority: City of Stirling […]
Milestone 9: First Floor Lockup đź“… Status: Work in Progress. Target Date: 19 December 2025 🏛 Authority: City of Stirling […]
Milestone 8: Roof Structure 📅 Status: Completed. Completion Date: 12 November 2025 🏛 Authority: City of Stirling (City of Stirling
Milestone 7: First Floor Brickwork đź“… Status: Completed on 26 September, after bricklaying delays due to the heavy winter rains.
Milestone 6: Suspended Slab Poured đź“… Completed: 20 June 2025 🏛 Authority: City of Stirling (City of Stirling – Welcome
Milestone 5: Ground Floor Brickwork Completed 📅 Date Completed: 11 April 2025 🏛 Authority: City of Stirling (City of Stirling
Milestone 4: Slab Poured đź“… Date Completed: 5 February 2025 🏛 Authority: City of Stirling (City of Stirling – Welcome
Milestone 3: Building Permit Issued đź“… Date Issued: 9 January 2025 🏛 Authority: City of Stirling (City of Stirling –
Milestone 2: DA Approved đź“… Date Received: 10 July 2024 🏛 Authority: City of Stirling (City of Stirling – Welcome
Milestone 1: Demolition Completed đź“… Date Completed: 17 June 2024 🏛 Authority: City of Stirling (City of Stirling – Welcome
23 Minilya St Innaloo Details of the Complex The 23 Minilya St complex in Innaloo is a modern, low-rise build-to-rent apartment complex