The 13th major milestone for the 23 Minilya Project:

βœ… Acces gates (scheduled)

βœ… Visitors’ bays and bin pad (scheduled)

βœ… Pedestrian pathways (scheduled)

βœ… Reticulation (scheduled)

βœ…Reticulation pre-lays (completed)

βœ… Mural and door artwork (scheduled)

βœ… Mural and door artwork design (completed)

βœ… Services infrastructure (in progress)

βœ… Driveway and crossover (in progress)

βœ… Paving of parking area (in progress)

βœ… Paving of courtyards (in progress)

βœ… L1 Pergola beams (completed)

βœ… Driveway pergola beams (completed)

βœ… Boundary walls (completed)