Our Projects
The 23 Minilya Project is an exciting residential development featuring a modern, low-rise build-to-rent apartment complex designed for sustainable living. It is a 2-storey apartment complex consisting of 7 units, with the look-and-feel of a townhouse complex. It is walking distance from the new City of Stirling CBD, which includes the Stirling train station and the Innaloo Shopping Centre. The site backs onto a large park and is within a 5km radius from Scarborough Beach and within a 10km radius from the Perth CBD.
Current News and Activities below, with more info and official milestone details available by clicking the “23 Minilya Project” link below
Current News and Activities at 23 Minilya

Milestone 9 & 11 Completed!
- Milestones 9 & 11 completed (First Floor Lockup and Ground Floor Lockup)
- Milestones 10, 12 & 13 now in Progress:
- Milestone 10: First Floor Fit-out (cabinetry, floor covers, wet areas, painting, window treatments, aircon, etc)
- Milestone 11: Ground Floor Fit-out (cabinetry, floor covers, wet areas, painting, window treatments, aircon, etc)
- Milestone 13: External Hardscaping (paving, pathways, boundary walls, fencing, gates and access control, reticulation pre-lays, reticulation, etc)
Project and Milestone Details:

Project Videos
Project Overview Photos (2-6 photos uploaded for each milestone, upon completion of the milestone)

Milestone 10 (Ground Floor Lockup) 
Milestone 10 (Ground Floor Lockup) 
Milestone 10 (Ground Floor Lockup) 
Milestone 10 (Ground Floor Lockup) 
Milestone 10 (Ground Floor Lockup) 
Milestone 10 (Ground Floor Lockup) 
Milestone 9 (First Floor Lockup) 
Milestone 9 (First Floor Lockup) 
Milestone 9 (First Floor Lockup) 
Milestone 9 (First Floor Lockup) 
Milestone 9 (First Floor Lockup) 
Milestone 9 (First Floor Lockup) 

Milestone 8 (Roof Structure) 
Milestone 8 (Roof Structure) 
Milestone 7 (First Floor Brickwork) 
Milestone 7 (First Floor Brickwork) 
Milestone 7 (First Floor Brickwork) 
Milestone 7 (First Floor Brickwork) 
Milestone 7 (First Floor Brickwork) 
Milestone 6 (Suspended Slab) – Freshly Poured 
Milestone 6 (Suspended Slab) 
Milestone 6 (Suspended Slab) – Pouring, with Steel Work and Pre-lays in the foreground 
Milestone 6 (Suspended Slab) – Queueing Concrete Trucks 
Milestone 6 (Suspended Slab) – Formwork 
Milestone 6 (Suspended Slab) – Pre-lay 
Milestone 5 (Ground Floor Brickwork) 
Milestone 5 (Ground Floor Brickwork) 
Milestone 5 (Ground Floor Brickwork) 
Milestone 4 (Slab) 
Milestone 4 (Slab) 
Milestone 3 (Building Permit) 
Milestone 2 (DA) 
Milestone 1 (Demolition) 
Milestone 1 (Demolition) 
Before (Front) 
Before (Back)