📍 Location: 23 Minilya Street, Innaloo WA 6018
📅 Construction Timeline: January 2025 – July 2026
🏗 Builder: Converge Design & Construct (Visit Website)
📖 Description:
The 23 Minilya Project is a residential development featuring a modern, low-rise build-to-rent apartment complex designed for sustainable living. It is a 2-storey apartment complex consisting of 7 units, with the look-and-feel of a townhouse complex. It is walking distance from the new City of Stirling CBD, which includes the Stirling train station and the Innaloo Shopping Centre. The site backs onto a large park and is within a 5km radius from Scarborough Beach and within a 10km radius from the Perth CBD.
Key Entities
- Developer and Owner: JBEM Pty Ltd (JBEM)
- Designer and Builder: Converge, Design and Construct (https://convergeconstruct.com/)
- Council: City of Stirling (City of Stirling – Welcome to the City of Stirling | view latest updates)
Major Project Milestones
Follow our journey as we progress through the key milestones of the project:
|
No |
Milestone |
Work Package |
Completed? |
|---|---|---|---|
|
1 |
Surveyor pegging, services disconnect, demolition permit, demolition, rubble removal and earthworks |
||
|
2 |
Concept design, council liaison, preliminary engineering reports, DA design, Development Application submitted and approved |
||
|
3 |
Working drawings, final engineering reports, landscape plan, building permit application and building permit issued |
||
|
4 |
Surveyor pegging, earthworks, drainage, pre-lays, steelwork, formwork, termite treatment, pouring the footings & slab |
||
|
5 |
Brickwork, bricking in door and window frames on ground floor |
||
|
6 |
Pre-lays, steelwork, formwork, pouring the columns and suspended slab |
||
|
7 |
WIP: Scaffolding, brickwork, first floor external rendering/painting |
||
|
8 |
Roof framing, roof sheeting, ducts and tubes, flashings and gutters, insulation |
||
|
9 |
External & internal plastering, glazing, hanging external doors, ceilings and insulation, first floor external texture coating and painting |
||
|
10 |
Hanging internal doors, cabinetry, benchtops, carpets and tiles, wet areas, blinds, electrical fittings, aircon, security, internal painting |
||
|
11 |
Ground floor roof framing and sheeting, tubes and ducts, internal plastering, glazing, hanging external doors, ceilings and insulation, ground floor external plastering, texture coating and painting |
||
|
12 |
Hanging internal doors, cabinetry, benchtops, carpets and tiles, wet areas, blinds, electrical fittings, aircon, security, internal painting |
||
|
13 |
Boundary walls, fencing, reticulation pre-lays, paving, reticulation installation, parking bays, visitors bays, bin pad, council services infrastructure |
||
|
14 |
Ordering plants, plant delivery, soil and fertilizer, planting and mulching, cleanup |
||
|
15 |
Project Completion & Handover |