Milestone 6: Suspended Slab Poured
📅 Completed: 20 June 2025
🏛 Authority: City of Stirling (City of Stirling – Welcome to the City of Stirling | view latest updates)
Overview
The sixth major milestone for the 23 Minilya Project involved:
✅ Steel work and form work for the columns, and pouring/curing the columns (completed)
✅ Form work and plumbing pre-lays completed
✅ Steel delivered and craned to L1; a site visit from Work Safe Australia
✅ Electrical pre-lays and steel work completed
✅ Suspended slab poured on Fri 23 May
✅Slab curing, removal of formwork and structural inspection.
Milestone Highlights: