Milestone 7: First Floor Brickwork

📅 Status: Completed on 26 September, after bricklaying delays due to the heavy winter rains. Target Date: 12 September 2025

🏛 Authority: City of Stirling (City of Stirling – Welcome to the City of Stirling | view latest updates)

Overview

The 7th major milestone for the 23 Minilya Project:

✅ Erection of scaffolding and installing a hoist (completed)

✅ Delivery of bricks, steel, window and door frames (completed)

✅ Electrical and plumbing pre-lays (completed)

✅Steel delivery, craning to first floor and welding (completed)

✅Raising scaffolding (completed)

✅ Bricklaying (completed)

Milestone Highlights: