MS4: Slab Poured – 23 Minilya Project
Milestone 4: Slab Poured 📅 Date Completed: 5 February 2025 🏛 Authority: City of Stirling (City of Stirling – Welcome […]
Milestone 4: Slab Poured 📅 Date Completed: 5 February 2025 🏛 Authority: City of Stirling (City of Stirling – Welcome […]
Milestone 3: Building Permit Issued 📅 Date Issued: 9 January 2025 🏛 Authority: City of Stirling (City of Stirling –
Milestone 2: DA Approved 📅 Date Received: 10 July 2024 🏛 Authority: City of Stirling (City of Stirling – Welcome
Milestone 1: Demolition Completed 📅 Date Completed: 17 June 2024 🏛 Authority: City of Stirling (City of Stirling – Welcome